LOCATION

Denver, CO

 

SIZE

117,000 sq. ft. Data Center

 

SCOPE

  • BAS System Complete Replacement
  • 3 – Daikin Air Cooled Chillers (Existing)
  • 1 – Daikin Air Cooled Chillers (New)
  • 2 – Evapco Fluid Cooler (Existing)
  • 1 – Evapco Fluid Cooler (New)
  • 10 – Added New CRAHs to Utility Rooms
  • 16 – Added New CRAHs to Data Hall #5
  • Added TST Storage Capacity
  • Added New Data Hall #5
  • Replace Valves and Instruments not Functional

FEATURES

  • Installed New BAS Controls Throughout Building Without Interruption
  • Looped Primary only Chilled Water Plant
  • 3 – 300 Ton Chillers
  • 1 – 300 Ton Chiller
  • 4 – Redundant Dedicated Chilled Water Pump Monitoring and Control
  • Generator Fuel System Monitoring
  • Generator Exhaust Damper Control
  • Generator Room, UPS Room, and Battery Room Monitoring
  • Battery Hydrogen Monitoring, Alarming, and Control
  • Energy Monitoring System
  • Redundant Data Floor Air Handling Units
  • VAVs, Fan Powered Boxes, and Fan Coil Units
  • Server Rack Temperature Monitoring System